Key facts
- Contractor
- Must be on HDB's Directory of Renovation Contractors (Renovation Control Rules 2006)Source: HDB
- General works
- 9am to 6pm, Monday to Saturday; none on Sundays or public holidaysSource: HDB
- Noisy works
- 9am to 5pm, weekdays only; at most 3 consecutive days of hackingSource: HDB
- Neighbour notice
- Written notice to flats within 2 units, at least 5 days before work startsSource: HDB
- Permit deadline
- 3 months (new blocks), 1 month (existing blocks), 2 weeks (windows only)Source: HDB
- New-flat toilets
- No removing toilet floor or wall finishes for 3 years from block completionSource: HDB
- CaseTrust deposit cap
- Initial deposit capped at 20% of contract; deposit performance bond requiredSource: CASE
- Small Claims Tribunals
- Up to $20,000 ($30,000 with consent); file within 2 yearsSource: Singapore Courts
This guide starts once you have the keys. For buying the flat, see BTO flats explained, BTO with your partner and Buying an HDB resale flat.
What a renovation costs
HDB does not publish renovation costs. The most detailed recent figures come from Qanvast, a renovation platform. It took the 2025 medians from 341 BTO and 449 resale projects on its site and added 1% to 2% for inflation to project 2026 costs:
| Flat | BTO | Resale |
|---|---|---|
| 3-room | $40,800 to $52,500 | $55,000 to $68,300 |
| 4-room | $50,000 to $60,000 | $70,000 to $81,600 |
| 5-room | $60,600 to $76,500 | $80,800 to $98,900 |
Treat these as a market benchmark, not a quote. SingSaver's May 2026 table, also based on Qanvast data, gives different ranges for the same flat types, so the spread is wide. Resale costs more because there is usually more to hack out, redo and rewire before the new work can start. To find your own number, get several itemised quotes for the same scope.
The HDB rules your contractor must follow
Use a DRC contractor. Under the Housing & Development (Renovation Control) Rules 2006, you may only hire contractors listed in HDB's Directory of Renovation Contractors (DRC). You can search the list with HDB's e-Service. Window work needs a BCA-approved window contractor, electrical work needs an EMA-licensed electrical worker, and air-con installation needs a BCA-trained installer.
Permits. Some works, such as demolishing walls, need HDB's written approval before they start. The contractor applies online with a floor plan of the proposed works. Work done without a required permit counts as unauthorised, and HDB can make you restore the flat to its original state. Works that need no permit still have to follow HDB's guidelines. For a new flat, you must open a utilities account with SP Services before HDB will grant a permit.
Deadlines once the permit is granted:
- Newly completed blocks: finish within 3 months.
- Existing blocks: finish within 1 month.
- Window works only: finish within 2 weeks.
Tell your HDB Branch when the works are done.
Working hours:
- General works: 9am to 6pm, Monday to Saturday. No work on Sundays or public holidays.
- Noisy works (demolishing walls, removing wall or floor finishes, cutting tiles, heavy drilling): 9am to 5pm on weekdays only. They are also banned on the eves of New Year's Day, Chinese New Year, Deepavali, Hari Raya Puasa and Christmas Day.
- Hacking and removing finishes may not run for more than 3 consecutive days. Only 2 HDB-approved handheld power tools may be used at a time.
- DIY: keep drilling and hammering between 7am and 10.30pm.
Neighbours. At least 5 days before work starts, give written notice to neighbours within 2 units of your flat. The Notice of Renovation must stay up outside your door until the work is finished.
New flats: leave the toilet tiles alone. The waterproofing under toilet floors stops leaks into the flat below. For 3 years from the block's completion date, you may not remove the toilet wall and floor finishes supplied by HDB or the developer. You can lay new tiles over the old floor with adhesive.
Work HDB does not allow includes:
- hacking structural walls, columns, beams or slabs
- loading the floor with more than 150kg per square metre
- plastering ceilings
- partitions made of combustible materials such as plywood
- raising the floor more than 50mm with concrete
- covering over void areas
- moving the refuse chute opening
- painting the common corridor
- awnings or fixtures outside the flat
- replacing full-height, 3/4-height or bay windows
- removing the safety railings or grilles that HDB installed
Some estates, such as DBSS precincts, have extra rules. Check yours on MyHDB Page.
Penalties. Owners who hire a non-DRC contractor or break HDB's renovation rules can be fined up to $5,000 if convicted. So can DRC contractors who break the rules, and anyone who poses as a DRC contractor. HDB can offer to compound an offence instead, but if the composition sum is not paid, the case goes to court. Putting a skip tank in an HDB car park without a permit can lead to a fine of up to $2,000 per offence for repeat offenders.
Debris. You pay for any Town Council haulage and debris removal. Where the Town Council does not offer it, your contractor must take the debris to an NEA-approved site.
Choosing a contractor or ID
DRC registration is a legal requirement, but it does not protect your money. CaseTrust accreditation from CASE (Consumers Association of Singapore) adds protection. An accredited renovation business must:
- buy a deposit performance bond, which protects your deposit if the firm closes or is wound up
- use the CaseTrust Standard Renovation Contract
- take no more than 20% of the total cost as the initial deposit, then collect the rest in stages as agreed milestones are reached
- show a breakdown of its prices and agree any variation with you in writing before that work starts
- give a 12-month workmanship warranty from completion and fix defects in that period
- attend CASE mediation if you ask for it
There are two schemes. One is CaseTrust's own. The other is a joint scheme with RCMA, open only to RCMA members, and its bond also covers the contract not being carried out. Check the firm's name, UEN and expiry date on CASE's directory before you sign. The directory also shows whether the firm is on HDB's DRC list.
Whatever firm you pick, follow the same rules as an accredited one: a deposit of 20% or less, payments tied to milestones, and every change in writing. HDB is not a party to your contract and will not settle disputes between you and your contractor.
When things go wrong
HDB advises agreeing on price, schedule and quality standards in writing at the start. If a dispute still comes up:
- Complain to CASE. Use the online form at complaints.case.org.sg or call 6277 5100. CASE says its officers reply within 5 working days.
- Mediation at CASE. It is voluntary and sessions last 2 hours. CASE says about 70% to 80% of cases are resolved. A CaseTrust-accredited firm must attend if you ask, and CaseTrust pays the firm's fee. Non-accredited firms can decline.
- Small Claims Tribunals. The tribunals hear renovation contracts as service contracts. The limit is $20,000, or $30,000 if both sides sign a Memorandum of Consent. You must file within 2 years of the event behind the claim, and lawyers cannot represent either side.
- Court for larger claims.
From keys to moving in
- Before key collection: get quotes, check the DRC list and CaseTrust status, and agree the design and payment milestones. Qanvast says owners often spend around $50,000 or more, so line up your financing early.
- New flat, on key collection: open your SP Services utilities account, because HDB needs it before granting a permit. Check the flat for defects and report them through the QR code in your Welcome Kit or at the temporary Building Service Centre. HDB fixes reported defects during the 1-year defects liability period. Report them before your contractor starts, so it is clear which problems came from the builder.
- Permit: your contractor applies. The clock starts when it is granted: 3 months for a new block, 1 month for an existing one.
- Notice: give neighbours written notice at least 5 days ahead and put up the Notice of Renovation.
- Works: noisy works run on weekdays only, so schedule hacking first. Qanvast's figures for typical project length are 6 to 10 weeks for a BTO and 8 to 11 weeks for a resale flat, depending on size.
- Handover: inspect the work against the contract before the final payment. Water-test bathrooms where tiles were replaced (HDB requires this) and keep a list of defects for the warranty period. Tell your HDB Branch the works are complete.
During the works, HDB suggests securing the flat with a close-shackled lock rather than a number lock, and not leaving appliances inside.